Maintenance economics
Downtime cost figures: which ones hold up
Most downtime statistics in circulation come from vendor surveys or have lost their source. This article traces the common ones, grades what they can support, and sets out how to work out the number that matters, which is the cost of an hour of downtime on your own equipment.
Published 6 min read9 sources
Written for maintenance managers · operations and plant managers · business owners and finance
The headline number
The most quoted figure comes from Siemens, which estimates that the world's 500 biggest companies lose almost $1.4 trillion a year to unplanned downtime, about 11% of their revenues.[1] It is a vendor's estimate, extrapolated from 181 online interviews with maintenance, engineering and IT staff at large manufacturers in four sectors between 2019 and 2023. It is a reasonable indication that downtime is expensive for very large plants and not much use for estimating the cost on any particular one.
The strongest number we found
In 2020 the US National Institute of Standards and Technology published an estimate of what maintenance costs American discrete manufacturers, and what poor maintenance costs them on top.
- US$57.3 bnMaintenance spend
- Machinery maintenance spending by US discrete manufacturers in 2016.[2]
- US$119.1 bnLosses from preventable maintenance issues
- Of which $18.1 billion was downtime and $100.2 billion lost sales from delays and defects. Same population, same year.[2]
- 3.3×Downtime, most reactive vs least
- Plants in the top quarter for reliance on reactive maintenance were associated with 3.3 times the downtime of those in the bottom quarter.[2]
- 16×Defects, same comparison
- The same plants were associated with 16 times more product defects.[2]
The caveats matter. The survey returned 85 responses, of which 71 were used. The downtime estimate carries a 90% confidence interval of $9.4 billion to $29.5 billion, and NIST notes that many of its sub-group comparisons are not statistically significant. The fair reading is an association: plants that run mostly reactively also report much more downtime and more defects. It does not show that changing one would change the other by the same amount.
Where a pump's cost sits
The pump industry's life-cycle guidance, produced with the US Department of Energy, says 'the initial purchase price is a small part of the life cycle cost for high usage pumps', and that 'depending upon the process, down time costs can be more significant than the energy or maintenance elements'.[3] On where the numbers should come from, it is direct:
“Whenever available, historical data is preferable to theoretical data from the equipment supplier.”
The Department of Energy's pumping-system guide lists 'frequent replacements of bearings and seals' among the five common signs that a pump is oversized for its duty, and warns that 'frequently replacing pump seals and bearings can keep a maintenance crew so busy that they overlook the system operating conditions that are causing most (or all) of the problems'.[4] The seal kit and the labour are the visible part of a repeat seal failure. The downtime, any process loss, and the operating condition left in place to damage the next seal are usually larger. The fault that keeps coming back works through that case.
Working out your own cost of downtime
A defensible figure for one asset is usually built from four parts, each of which a site can estimate from its own records. The weights differ a great deal between a duty pump with an installed standby, a crusher that stops a whole process line, and an excavator on a project with a hire agreement.
- Lost output or the cost of replacing it. Production foregone per hour, or the cost of the substitute: hired plant, tankered water, contractors, overtime to catch up. If an installed standby carries the duty, the immediate figure may be close to nil, and the real cost is the risk carried while the standby runs alone.
- Costs that continue while the asset is down. Crews standing by, hire charges that keep running, idle downstream equipment.
- The repair itself. Labour, parts, contractors and expediting. Breakdown repairs often cost more than the same repair planned, because of call-out rates, freight and the secondary damage a failure in service causes.
- Consequences. Contract penalties, rework, licence or environmental consequences, and safety exposure. These are often the largest and the hardest to estimate, and worth stating as a range rather than a single number.
Multiplying that hourly figure by the hours lost to one asset's repeat failures in a year is often enough to settle whether an investigation, a design change or a replacement is worth funding. The hours and the repeat count come from the maintenance history, if it records failures against the asset and component rather than as free-standing jobs.
Deferred work and backlog
The US Government Accountability Office reported in 2025 that federal deferred maintenance and repair backlogs had more than doubled, from $171 billion to $370 billion, between 2017 and 2024, and warned that assets left to deteriorate 'need premature replacement, which can be significantly more expensive than if maintenance and repairs were done when originally scheduled'.[5]
The UK offshore regulator, inspecting nearly 100 installations, reported 'high levels of both safety- and non-safety-critical backlog and poor backlog management' across the industry, and maintenance records whose quality was 'often inconsistent, particularly in recording the "as found" condition rather than the "maintained" condition and in reporting the cause of failure'.[6] Those two fields, the condition found and the cause, are what allow a backlog to be ranked by risk rather than by age.
When the asset record is wrong
In 2010 a gas transmission pipeline ruptured in San Bruno, California. Eight people were killed and 38 homes destroyed. The company's records described the failed section as pipe with no welded seam; investigators found it had seam welds. The US National Transportation Safety Board concluded the operator's integrity management program was deficient in part because it 'was based on incomplete and inaccurate pipeline information'.[7] Risk ranking, inspection methods and pressure limits had all been set from that record.
The first shift after a service
Maintenance carries its own risk, and some of it is measurable. The NSW Resources Regulator reviewed 18 fires on mobile plant at open-cut coal mines between April and October 2021. Nine happened within the first shift after the plant was returned to service, and ten came from workmanship errors 'likely to have been detected by visual inspection by a supervisor or a short period of workshop commissioning'.[8] The cost of a check before the first shift is small beside the cost of a fire. Three decisions before a machine goes back to work covers what that check involves.
Figures we could not trace
These are widely repeated, and we could not trace any of them to an original source with a stated method, so we do not use them:
- That reactive maintenance costs three to five times as much as planned maintenance.
- Percentage savings from moving off reactive maintenance, often quoted at 12–18%, which trace back to unnamed 'studies'.
- A fixed share of pump failures caused by seals.
- The share of a technician's day spent searching for information. We found no maintenance-specific measurement with a stated method.
None of the studies here measured Mainte, and we publish no savings figure for it. The method above gives a more useful number for your own plant. The HSE's ageing-plant guidance adds a test of whether your records can support it: they should 'differentiate between 20 new seals on one pump, and 20 new seals over several pumps'.[9]
Sources
- [1]The True Cost of Downtime 2024 · Siemens AG (Senseye) · 2024 · Vendor-sponsored survey reportBased on 181 online interviews at large industrial organisations, April 2019 to March 2023, extrapolated to the Fortune Global 500.
- [2]Economics of Manufacturing Machinery Maintenance: A Survey and Analysis of U.S. Costs and Benefits (NIST AMS 100-34) · D. Thomas and B. Weiss, National Institute of Standards and Technology (US) · June 2020 · Government research reportUS discrete manufacturing (NAICS 321–339, excluding 324 and 325), 2016, US dollars. 85 survey responses returned, 71 used.
- [3]Pump Life Cycle Costs: A Guide to LCC Analysis for Pumping Systems, executive summary · Hydraulic Institute, Europump and the US Department of Energy · January 2001 · Industry and government guidance
- [4]Improving Pumping System Performance: A Sourcebook for Industry (second edition) · US Department of Energy and the Hydraulic Institute · May 2006 · Government technical guidance
- [5]Federal Real Property: Disposing of Unneeded Facilities Could Help Reduce Maintenance Backlog (GAO-25-108400) · US Government Accountability Office · 9 April 2025 · Government audit testimony
- [6]Key Programme 3: Asset Integrity Programme · Health and Safety Executive, Offshore Division (UK) · November 2007 · Regulator inspection programme reportTargeted inspections of nearly 100 offshore installations, about 40% of the total, 2004–2007.
- [7]Pacific Gas and Electric Company Natural Gas Transmission Pipeline Rupture and Fire, San Bruno, California (NTSB/PAR-11/01) · US National Transportation Safety Board · Adopted 30 August 2011 · Federal accident investigation report
- [8]Safety Bulletin SB21-11: Fires occur after servicing mobile plant · Resources Regulator, NSW · December 2021 · Regulator safety bulletin
- [9]Plant ageing: management of equipment containing hazardous fluids or pressure (RR509) · Health and Safety Executive (UK); prepared by TWI, ABB Engineering Services, SCS and Allianz Cornhill Engineering · 2006 · Research report commissioned by the regulatorSection 2.4.2. Internet Archive copy.